-
RAIL
REGULATOR GRANTS BARS A EUROPE WIDE FREIGHT AND PASSENGER LICENCE : Weardale
Railways majority shareholder, British American Rail Services also owns,
as a UK subsidiary, Devon and Cornwall Railways.(DCR). On the 26th
August the Office of Rail Regulation published
notice of its intent to grant DCR European passenger and freight operating
licences. This kicks off a 28 day period for public comment;
barring any major objections, and given that Devon and Cornwall has
certain insurance coverage and industry agreements in place at the end of
that period, the company will then be licenced to operate trains
throughout the United Kingdom. Ed Ellis, Company President, pointed out
“Once licenced, DCR will still need to apply to operate trains over a
specific route, but this is a major step forward in being able to provide
freight and passenger services over the national U.K. rail network. This
is the culmination of many months of effort by BARS/DCR staff and in the
case of Weardale brings the possibility of extending our existing
passenger services onto the Network much closer. It also has implications
for developing the freight services along the line.”
|
|

|

|
|
DCR
Loco 31452 in the suburban platforms at Kings Cross.
Thanks to
Wayne Radford
for this photo. See his other photographs
at: http://wayne-radford.fotopic.net/p61682361.htm |
31452
at East Leake on the Great Central Railway.
Thanks to AndrewThomas for this photo. See this and his
other photos at :
http://andrewthomas.fotopic.net/ |
- WOLSINGHAM
SHOW : SPECIAL EXTRA SERVICES
TO SHOWGROUND :
September 4th and 5th will see a greatly
augmented service on the Weardale Railway to serve a special
temporary platform at the Wolsingham showground. This has involved
some intricate timetable planning as it is intended to use
both 141 diesel multiple units operating independently with the
additional complication of fitting in a Charter from Dundee and
Edinburgh on the Saturday. On Saturday (4th) there will
be eight services to and from Bishop Auckland during the day, four
terminating at the Wolsingham Showground
while four will continue on to and from Stanhope. On the
Sunday there will be seven services to and from Bishop Auckland with
three running on to and from Stanhope. Our normal community rail
fares will apply (£5.30 return from Bishop Auckland) For these purposes the showground will be treated as though it were
Wolsingham. Anyone
travelling to or from the showground to Wolsingham itself will be
charged 50p. Please be ready to point out to intending passengers
that the temporary platform has only a step access and is unsuitable
for disabled passengers. For more information on the show, see : http://www.wolsinghamshow.com/index.htm
- CHARTER
TRAIN FROM SCOTLAND WILL ALSO CARRY
LOCAL PASSENGERS : On
Saturday 4th
September a Charter train operated by the Scottish Railway
Preservation Society will run from Dundee and stations through
Edinburgh and Berwick to York and will then double back to visit
Weardale .It will utilise the SRPS maroon carriages and be diesel
hauled throughout. First Class dining facilities are also being
provided. A
limited number of tickets will be available from York
to Weardale at £25 (or £35 First Class). In addition
arrangements have been made for the train to call at the Weardale
Railway platform at Bishop Auckland to convey passengers
to Wolsingham showground and Stanhope. Passengers travelling
to the showground will need to pay the normal community rail fare of
£5.50 return, those travelling to Stanhope will be required to pay
the Heritage supplement. The train is provisionally scheduled to
leave Bishop Auckland at 13.35 and arrive at the showground at 14.05 and Stanhope at 14.30. It is due to leave Stanhope at
16.00 and the showground at 16.40 arriving at Bishop Auckland at
17.10. Please note these times are provisional as we have yet to
receive the final timings from Network Rail – so please check this
website before travel - Timetables
- WEARDALE
RAILWAYS TO PROVIDE SERVICES TO STANHOPE SHOWGROUND : Stanhope
show takes place on the weekend following the Wolsingham show, on
September11, 12th.Again a temporary platform will be used
and the service of trains to and from Bishop Auckland will be
augmented. For details please see the Timetables page as
shown above. For information on the Show, see :
http://www.stanhopeshow.com/whats_on.htm

- IT
IS AUGUST : MUST BE TIME FOR SANTA : Well
it is on the Weardale Railway. Tickets are now on sale – see the
website for details, prices and times – and this year you can also
book directly online. There are other innovations planned for this
year. The ‘Pullman’ coach Nina will be deployed
and a supplement charged for First Class travel with service
at your seat. As last year, groups of passengers will be able to pre
reserve a Standard
Class compartment – at a small extra charge . There will be two
train services on each of 12 operating days, plus a single morning
service on December 24th. One service each day will have
a connecting service to and from Bishop Auckland. It is planned to
operate a Christmas Market in the car park at Stanhope. The Café,
Gift shop and Model Railway will also be open. One other option,
still being explored , is to use the Junior Club coach, classroom
end, as Santa’s Grotto – this would be placed in the bay at the
east end of the up platform, thus all the main activities could be
undertaken without crossing the footbridge. To obtain the full
information on how to book please visit Santa's
Page.
- DEPOT
NEWS : While
work proceeds on the applications and licences for the coal loading facility, opportunity has been taken to
rationalise the layout of other parts of the Depot area. This will
include moving the existing storage containers and staff
accommodation to the North West of the site away from the loading
area and upgrading the staff facilities in a new amenity block.
- DARTMOOR
RAILWAY UTILISING FORMER YUGOSLAVIAN STEAM : Our
sister company in Devon, the Dartmoor Railway, which in the summer
normally operates a five days/week diesel ‘thumper’ service from
Okehampton station has brought in a
Yugoslav built ‘USA’ tank engine to run a steam service
for two weeks from August 21st. This
type of loco is no stranger to the line as they worked at Meldon
Quarry until March 1967. The locomotive will return to the Mid-Hants
Railway in early September. See photos below :-
|
|
|
|
‘USA’
class 62 tank 300075 at Okehampton
Station during
its two week stay at the Dartmoor Railway this August.
|
30075
stating the climb from Okehampton towards Meldon Quarry.
( Both Photos : Bob Bunyan)
|
|
·
THE
COAL LOADING TERMINAL : FIRST STEPS
:
Donald
Heath reports
:- Having received planning permission
for the construction and operation of a coal loading terminal at the
Wolsingham Depot, the Company now has to “make it happen” in
accordance with the conditions contained within the consent. To do this,
a project “kick off” meeting was held at Bishop Auckland on August 5th.
Attended by most of the Weardale staff who will be involved in the work
necessary to not only get the first train off to its destination but,
also, to keep the operation going on a daily basis, the project team
made a very good start in identifying the myriad of tasks that will have
to be done and, equally importantly, allocating them to individuals to
do them within set time scales. In headline terms the activities can be
grouped as follows:
1.
Work to get the Wolsingham depot site adapted to include a coal loading
terminal;
2.
Track and other railway works necessary at Wolsingham for coal trains to
use the facilty.
3.
Railway works at Bishop Auckland to accommodate coal trains running on and
off the national network
whilst facilitating the continued operation of our
Community Rail service;
4.
The alterations which will be needed to our existing operational
arrangements so as cater for the additional trains
5.
A review of the existing infrastructure to ascertain what strengthening
will be necessary to cope with the very big increase in annual tonnage
that it will have to carry; and,
6.
Completion of all the further studies required by the County Council.
It will also be
necessary to have detailed discussions with Network Rail and the Freight
Operating Company which will run the coal trains to their destination(s)
on the timings of these trains on and off the national network as well
as the modus operandi which will be somewhat different to that
associated with the occasional excursion train that has so far used the
connecting line between the two companies.
The tasks described
above were allocated to individuals to get on with. David Million has
been appointed the project manager to coordinate all of the work streams
described above and he started work on August 23rd.
The first project
progress meeting was held on August 18th., and further
progress meetings will be held at fortnightly intervals. Initially,
these are focusing on confirming the specifications for the works to be
done with programming and contractual arrangements being developed close
behind.
Further reports will follow as and when there is significant progress to
report.
-
No 40 : RESTORATION
WORK CONTINUES : The work on two of the axle box bearings will be
completed in the next three days. However on inspection of the two
remaining as yet un-restored bearings our expert was of the opinion
that to replace them on the newly re-machined axles would be unwise
– it was felt safer to have the bearings re-machined from castings
made by melting down the old bearings. This will involve further delay
and although every effort will be made to have this work finished
before the War on the Line event, this can no longer be guaranteed.
 |
 |
|
No
40 in the Wolsingham Depot raised on the jacks
while
undergoing work on the axles and bearings. |
No
40 with one of the two re-machined axles.
( Both
photos : Norman Swindle ) |
-
BISHOP
AUCKLAND STATION-CONNECTING THE PLATFORMS : The
present temporary arrangement of
a separate platform linked by a roundabout footpath may be replaced
in the near future. Network Rail (NR) have agreed in principle to
move to a better design. This may happen in two stages, First a
direct path on railway land between the two platforms. This
obviously means working on NR
land and will need detailed design approval and the use of a NR
approved contractor. We hope to use RMS for this work as it is
already approved for Network operations.
Discussions are also ongoing with Durham County Council
Transport department on planned longer term improvements at Bishop
Auckland – more on this later.
 |
 |
|
Drainage
works underway on the land between the two
platforms
– this is where the planned linking path could
be
placed. |
The
Griddle Car as you have never seen it before. It will
emerge in
the BR ‘blood and custard’ livery. ( Both Photos
: Norman Swindle) |
-
FATALITY
ON THE BISHOP LINE : A British Transport Police
investigation is underway after a fatality on the Bishop Auckland
– Darlington line on April 11th. A man was knocked down
by the 9.25am train from Bishop Auckland
near the Dabble Duck Industrial Estate, half-a-mile outside Shildon,
Northern Rail operated a replacement bus service along the route
between Bishop
Auckland and Darlington
until emergency services had completed their work.
|
 |
|
No
Newsletter is complete without a Photo from John Lewins. This time he
has found a new viewpoint of the River Wear Bridge
immediately
to the east of the Depot connection, here with the Class 73 pulling the
Heritage stock on the day of the Morris
Minor Rally, August 15th. |
-
JUNIOR
CLUB NEWS : The newly established Bishop Auckland branch
members had their first outing – by train of course – to London. They
travelled First Class, courtesy of East Coast Railways and were led by
Dave Million and Mike Wilkinson and visited the London Transport Museum,
Hamleys, Buckingham Palace and the new international terminal at St
Pancras station. We hope to see more of these youngsters helping out on
our busy Show service days. Meanwhile work is continuing on the Junior
Clubs restoration of Coach 5226. All windows have been reinstalled and
work on the interior of both the ‘classroom’ and the Model railway
room is now complete. The juniors today added the finishing touches to
both areas by fixing the large train picture boards that were donated by
East Coast Main Line. The picture boards are both approximately 14
ft long and depict a National Express East Coast train and a GNER train.
There remains some further electrical work and also some exterior bodywork
repairs to be completed before repainting.
 |
 |
|
New
recruits : the members of the Bishop Auckland Branch of the WRJc on
their trip to London
beside a well-known
landmark and in the London
Transport museum. (Both Photos ; Dave Million) |
|
|
The Weardale
Railway Trust, in County Durham, needs at least £90,000 to get its 1954 No40
locomotive in working order. The engines’ boiler certificate is due for
renewal in 2012 and the railways’ 90-plus volunteers need the cash for its
maintenance. The railway, which now offers a passenger service connecting
Wolsingham to Bishop
Auckland, is putting up £55,000 and is appealing for help to raise the
remaining £40,000 needed for the work.
People can donate money or buy gifts, which include photographs of the No40,
footplate rides and copies of railway history books. Trevor Hewitt, treasurer
of Weardale Railway Trust, said: “This is a piece of history and a way of
keeping industrial and rail history alive. “A lot of railways will have the
same aims, but if we didn’t put the effort in then these things would die
out. We bought this engine from a railway in Essex, so it has come back home
to operate in its homeland in the North-East.”
To help the fund, visit weardale-railway.org.uk or call
01388-526203.
Courtesy : Northern Echo : 12th August
"A MUSEUM provided the platform yesterday
to help promote a new set of stamps celebrating Great British Railways.
Locomotion: The National Railway Museum, in Shildon,
County Durham, helped the Royal Mail launch the stamps, which go on sale
today. The stamps include a 1929 photo of the London North-East Region’s
Class A1 loco Royal Lancer. Duncan Edwards, an explainer at the museum, holds
an enlargement of one of the stamps which go on sale today."
Courtesy : Northern Echo
: 19th August
|
 |
 |
|
Trevor
Hewitt at the footplate of No 40.
|
The new
stamp launched at
Locomotion.
(Both Photos : Northern Echo ) |
-
NAME
THE COACH COMPETION EXTENDED : Dasvid
Million reports : Due to the
delaying finalising 5226 the “Name the Coach” competition has
been extended until 30th September 2010. For an entry fee of £2
(with profits going towards project 5226), the winning entry will
receive a goody pack including Weardale Railway Tie, set of 4 GNER
branded wine glasses (heavy version), 4 rare GNER branded tumblers,
National Express ice bucket, National Express mug and an East Coast
trains mouse mat. Entries with cheque, payable to “WRJC” should
be sent to:-
Project 5226 Competition, Weardale Railway Junior Club, Stanhope
Station, Station Road, Stanhope, Co. Durham. DL13 2YS
|
|
Edited
by Gerry Mudd
Comments, suggestions, contributions, corrections all
welcomed.
gcmudd@ntlworld.com
or 01932 889 811 or 07773 800 554 |